Uma proposta de integração do modelo BIM ao sistema Last Planner
| Ano de defesa: | 2017 |
|---|---|
| Autor(a) principal: | |
| Orientador(a): | |
| Banca de defesa: | , |
| Tipo de documento: | Dissertação |
| Tipo de acesso: | Acesso aberto |
| Idioma: | por |
| Instituição de defesa: |
Pontifícia Universidade Católica de Goiás
|
| Programa de Pós-Graduação: |
Programa de Pós-Graduação STRICTO SENSU em Engenharia de Produção e Sistemas
|
| Departamento: |
Escola de Engenharia::Curso de Engenharia de Produção
|
| País: |
Brasil
|
| Palavras-chave em Português: | |
| Palavras-chave em Inglês: | |
| Área do conhecimento CNPq: | |
| Link de acesso: | https://tede2.pucgoias.edu.br/handle/tede/3719 |
Resumo: | This research had as main point to use the Building Information Modeling (BIM), as an integrated form with the logic of the Last Planner system in relation to the planning and control of the production in companies of the civil construction sector and, with that, a model that promotes this integration in order to improve efficiency in medium and short term planning, where the construction of the integration model involves the development of a plug-in for Revit®, capable of making the information available in a database also fed by other software, here titled “L7”, through which it becomes possible to insert the analytic structure of a work and other information about the consumption of the inputs and, thus, make it possible to establish the relation between each geometric element and their needs for manpower and material, making explicit the restrictions when training the Lookahead through visual management. The methodological approach adopted was Design Science Research, whose main objective is to develop an artifact capable of solving a real and relevant problem and, thus, to promote the advance of the theoretical knowledge about the subject and to contribute to the operation within the companies. The evaluation of the constructed model was made through an empirical study in a work into a mall of a construction company in Goiás, followed by two services in the formation of the Lookahead of the month of January and the work week plan of the four weeks. It was possible, through visual color management, to check tasks that had material and/or labor constraints, facilitating the formatting of medium-term planning and improving the efficiency of short-term planning. |
| id |
PUC_GO_bec76e3b6fb4c068b36f10e6517f2eee |
|---|---|
| oai_identifier_str |
oai:ambar:tede/3719 |
| network_acronym_str |
PUC_GO |
| network_name_str |
Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás) |
| repository_id_str |
|
| spelling |
Machado, Ricardo Luizhttp://lattes.cnpq.br/4103684476705320Mendes Junior, Ricardohttp://lattes.cnpq.br/7584962183660586Luz, Marta Pereira dahttp://lattes.cnpq.br/5995967458007910http://lattes.cnpq.br/1615025485578236Rodrigues, Priscilla Borges de Freitas2017-06-29T13:25:07Z2017-03-23Rodrigues, Priscilla Borges de Freitas. Uma proposta de integração do modelo BIM ao sistema Last Planner. 2017. 147 f. Dissertação (Programa de Pós-Graduação STRICTO SENSU em Engenharia de Produção e Sistemas) - Pontifícia Universidade Católica de Goiás, Goiânia - GO.https://tede2.pucgoias.edu.br/handle/tede/3719This research had as main point to use the Building Information Modeling (BIM), as an integrated form with the logic of the Last Planner system in relation to the planning and control of the production in companies of the civil construction sector and, with that, a model that promotes this integration in order to improve efficiency in medium and short term planning, where the construction of the integration model involves the development of a plug-in for Revit®, capable of making the information available in a database also fed by other software, here titled “L7”, through which it becomes possible to insert the analytic structure of a work and other information about the consumption of the inputs and, thus, make it possible to establish the relation between each geometric element and their needs for manpower and material, making explicit the restrictions when training the Lookahead through visual management. The methodological approach adopted was Design Science Research, whose main objective is to develop an artifact capable of solving a real and relevant problem and, thus, to promote the advance of the theoretical knowledge about the subject and to contribute to the operation within the companies. The evaluation of the constructed model was made through an empirical study in a work into a mall of a construction company in Goiás, followed by two services in the formation of the Lookahead of the month of January and the work week plan of the four weeks. It was possible, through visual color management, to check tasks that had material and/or labor constraints, facilitating the formatting of medium-term planning and improving the efficiency of short-term planning.Esta pesquisa envolveu-se com a utilização da modelagem da informação da construção (BIM) de maneira integrada à lógica do Last Planner no planejamento e controle da produção em empreendimentos do setor da construção civil. Para isso, a investigação teve como objetivo principal construir um modelo BIM integrador, de forma a atuar na melhoria do planejamento de médio e curto prazo. A construção do modelo de integração passou pelo desenvolvimento de um plug-in para o software Revit®, capaz de disponibilizar informações em um banco de dados alimentado por outro software de planejamento. O modelo BIM estruturado tornou possível estabelecer a relação entre cada elemento geométrico do projeto arquitetônico e suas necessidades de materiais, mão-deobra e especificações de projeto. A abordagem metodológica adotada na pesquisa foi a Design Science Research. A avaliação do modelo construído foi feita em um estudo empírico em obra de grande porte do setor de edificações. Foi possível, através da gestão visual, verificar as tarefas que possuíam restrições em relação a materiais, mão-de-obra e detalhamento de projeto, facilitando a elaboração do planejamento de médio prazo e melhorando a eficiência do planejamento de curto prazo.Submitted by admin tede (tede@pucgoias.edu.br) on 2017-06-29T13:25:06Z No. of bitstreams: 1 PRISCILLA BORGES DE FREITAS RODRIGUES.pdf: 3855875 bytes, checksum: 11d800e90a7d8e85c9925dfdaa032c34 (MD5)Made available in DSpace on 2017-06-29T13:25:07Z (GMT). No. of bitstreams: 1 PRISCILLA BORGES DE FREITAS RODRIGUES.pdf: 3855875 bytes, checksum: 11d800e90a7d8e85c9925dfdaa032c34 (MD5) Previous issue date: 2017-03-23application/pdfhttps://tede2.pucgoias.edu.br/retrieve/11276/PRISCILLA%20BORGES%20DE%20FREITAS%20RODRIGUES.pdf.jpgporPontifícia Universidade Católica de GoiásPrograma de Pós-Graduação STRICTO SENSU em Engenharia de Produção e SistemasPUC GoiásBrasilEscola de Engenharia::Curso de Engenharia de ProduçãoModelagem da informação da construção; BIM; Last Planner; Planejamento e controle da produção; Revit®.Construction information modeling; Last Planner; Planning and production control; Plug-in for Revit®. ivENGENHARIAS::ENGENHARIA DE PRODUCAOUma proposta de integração do modelo BIM ao sistema Last Plannerinfo:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/masterThesisinfo:eu-repo/semantics/openAccessreponame:Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás)instname:Pontifícia Universidade Católica de Goiás (PUC-GO)instacron:PUC_GOTHUMBNAILPRISCILLA BORGES DE FREITAS RODRIGUES.pdf.jpgPRISCILLA BORGES DE FREITAS RODRIGUES.pdf.jpgimage/jpeg2831http://localhost:8080/tede/bitstream/tede/3719/4/PRISCILLA+BORGES+DE+FREITAS+RODRIGUES.pdf.jpg160f5430a6ff7fb452f91a4138acc112MD54TEXTPRISCILLA BORGES DE FREITAS RODRIGUES.pdf.txtPRISCILLA BORGES DE FREITAS RODRIGUES.pdf.txttext/plain190380http://localhost:8080/tede/bitstream/tede/3719/3/PRISCILLA+BORGES+DE+FREITAS+RODRIGUES.pdf.txt9be024a120fcddd276c45f2350974549MD53ORIGINALPRISCILLA BORGES DE FREITAS RODRIGUES.pdfPRISCILLA BORGES DE FREITAS RODRIGUES.pdfapplication/pdf3855875http://localhost:8080/tede/bitstream/tede/3719/2/PRISCILLA+BORGES+DE+FREITAS+RODRIGUES.pdf11d800e90a7d8e85c9925dfdaa032c34MD52LICENSElicense.txtlicense.txttext/plain; charset=utf-82001http://localhost:8080/tede/bitstream/tede/3719/1/license.txtfd9262f8b1e1c170dee71e4fbec6b16cMD51tede/37192025-09-24 09:27:27.023oai:ambar: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 Digital de Teses e Dissertaçõeshttp://tede2.pucgoias.edu.br:8080/http://tede2.pucgoias.edu.br:8080/oai/requesttede@pucgoias.edu.bropendoar:65932025-09-24T12:27:27Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás) - Pontifícia Universidade Católica de Goiás (PUC-GO)false |
| dc.title.eng.fl_str_mv |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| title |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| spellingShingle |
Uma proposta de integração do modelo BIM ao sistema Last Planner Rodrigues, Priscilla Borges de Freitas Modelagem da informação da construção; BIM; Last Planner; Planejamento e controle da produção; Revit®. Construction information modeling; Last Planner; Planning and production control; Plug-in for Revit®. iv ENGENHARIAS::ENGENHARIA DE PRODUCAO |
| title_short |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| title_full |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| title_fullStr |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| title_full_unstemmed |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| title_sort |
Uma proposta de integração do modelo BIM ao sistema Last Planner |
| author |
Rodrigues, Priscilla Borges de Freitas |
| author_facet |
Rodrigues, Priscilla Borges de Freitas |
| author_role |
author |
| dc.contributor.advisor1.fl_str_mv |
Machado, Ricardo Luiz |
| dc.contributor.advisor1Lattes.fl_str_mv |
http://lattes.cnpq.br/4103684476705320 |
| dc.contributor.referee1.fl_str_mv |
Mendes Junior, Ricardo |
| dc.contributor.referee1Lattes.fl_str_mv |
http://lattes.cnpq.br/7584962183660586 |
| dc.contributor.referee2.fl_str_mv |
Luz, Marta Pereira da |
| dc.contributor.referee2Lattes.fl_str_mv |
http://lattes.cnpq.br/5995967458007910 |
| dc.contributor.authorLattes.fl_str_mv |
http://lattes.cnpq.br/1615025485578236 |
| dc.contributor.author.fl_str_mv |
Rodrigues, Priscilla Borges de Freitas |
| contributor_str_mv |
Machado, Ricardo Luiz Mendes Junior, Ricardo Luz, Marta Pereira da |
| dc.subject.por.fl_str_mv |
Modelagem da informação da construção; BIM; Last Planner; Planejamento e controle da produção; Revit®. |
| topic |
Modelagem da informação da construção; BIM; Last Planner; Planejamento e controle da produção; Revit®. Construction information modeling; Last Planner; Planning and production control; Plug-in for Revit®. iv ENGENHARIAS::ENGENHARIA DE PRODUCAO |
| dc.subject.eng.fl_str_mv |
Construction information modeling; Last Planner; Planning and production control; Plug-in for Revit®. iv |
| dc.subject.cnpq.fl_str_mv |
ENGENHARIAS::ENGENHARIA DE PRODUCAO |
| description |
This research had as main point to use the Building Information Modeling (BIM), as an integrated form with the logic of the Last Planner system in relation to the planning and control of the production in companies of the civil construction sector and, with that, a model that promotes this integration in order to improve efficiency in medium and short term planning, where the construction of the integration model involves the development of a plug-in for Revit®, capable of making the information available in a database also fed by other software, here titled “L7”, through which it becomes possible to insert the analytic structure of a work and other information about the consumption of the inputs and, thus, make it possible to establish the relation between each geometric element and their needs for manpower and material, making explicit the restrictions when training the Lookahead through visual management. The methodological approach adopted was Design Science Research, whose main objective is to develop an artifact capable of solving a real and relevant problem and, thus, to promote the advance of the theoretical knowledge about the subject and to contribute to the operation within the companies. The evaluation of the constructed model was made through an empirical study in a work into a mall of a construction company in Goiás, followed by two services in the formation of the Lookahead of the month of January and the work week plan of the four weeks. It was possible, through visual color management, to check tasks that had material and/or labor constraints, facilitating the formatting of medium-term planning and improving the efficiency of short-term planning. |
| publishDate |
2017 |
| dc.date.accessioned.fl_str_mv |
2017-06-29T13:25:07Z |
| dc.date.issued.fl_str_mv |
2017-03-23 |
| dc.type.status.fl_str_mv |
info:eu-repo/semantics/publishedVersion |
| dc.type.driver.fl_str_mv |
info:eu-repo/semantics/masterThesis |
| format |
masterThesis |
| status_str |
publishedVersion |
| dc.identifier.citation.fl_str_mv |
Rodrigues, Priscilla Borges de Freitas. Uma proposta de integração do modelo BIM ao sistema Last Planner. 2017. 147 f. Dissertação (Programa de Pós-Graduação STRICTO SENSU em Engenharia de Produção e Sistemas) - Pontifícia Universidade Católica de Goiás, Goiânia - GO. |
| dc.identifier.uri.fl_str_mv |
https://tede2.pucgoias.edu.br/handle/tede/3719 |
| identifier_str_mv |
Rodrigues, Priscilla Borges de Freitas. Uma proposta de integração do modelo BIM ao sistema Last Planner. 2017. 147 f. Dissertação (Programa de Pós-Graduação STRICTO SENSU em Engenharia de Produção e Sistemas) - Pontifícia Universidade Católica de Goiás, Goiânia - GO. |
| url |
https://tede2.pucgoias.edu.br/handle/tede/3719 |
| dc.language.iso.fl_str_mv |
por |
| language |
por |
| dc.rights.driver.fl_str_mv |
info:eu-repo/semantics/openAccess |
| eu_rights_str_mv |
openAccess |
| dc.format.none.fl_str_mv |
application/pdf |
| dc.publisher.none.fl_str_mv |
Pontifícia Universidade Católica de Goiás |
| dc.publisher.program.fl_str_mv |
Programa de Pós-Graduação STRICTO SENSU em Engenharia de Produção e Sistemas |
| dc.publisher.initials.fl_str_mv |
PUC Goiás |
| dc.publisher.country.fl_str_mv |
Brasil |
| dc.publisher.department.fl_str_mv |
Escola de Engenharia::Curso de Engenharia de Produção |
| publisher.none.fl_str_mv |
Pontifícia Universidade Católica de Goiás |
| dc.source.none.fl_str_mv |
reponame:Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás) instname:Pontifícia Universidade Católica de Goiás (PUC-GO) instacron:PUC_GO |
| instname_str |
Pontifícia Universidade Católica de Goiás (PUC-GO) |
| instacron_str |
PUC_GO |
| institution |
PUC_GO |
| reponame_str |
Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás) |
| collection |
Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás) |
| bitstream.url.fl_str_mv |
http://localhost:8080/tede/bitstream/tede/3719/4/PRISCILLA+BORGES+DE+FREITAS+RODRIGUES.pdf.jpg http://localhost:8080/tede/bitstream/tede/3719/3/PRISCILLA+BORGES+DE+FREITAS+RODRIGUES.pdf.txt http://localhost:8080/tede/bitstream/tede/3719/2/PRISCILLA+BORGES+DE+FREITAS+RODRIGUES.pdf http://localhost:8080/tede/bitstream/tede/3719/1/license.txt |
| bitstream.checksum.fl_str_mv |
160f5430a6ff7fb452f91a4138acc112 9be024a120fcddd276c45f2350974549 11d800e90a7d8e85c9925dfdaa032c34 fd9262f8b1e1c170dee71e4fbec6b16c |
| bitstream.checksumAlgorithm.fl_str_mv |
MD5 MD5 MD5 MD5 |
| repository.name.fl_str_mv |
Biblioteca Digital de Teses e Dissertações da PUC_GOAIS (TEDE-PUC Goiás) - Pontifícia Universidade Católica de Goiás (PUC-GO) |
| repository.mail.fl_str_mv |
tede@pucgoias.edu.br |
| _version_ |
1856222749349904384 |